Excavation Volume

The total volume of earth to be removed from a site, calculated from dimensions and depth of the dig.

Excavation volume determines how much soil must be removed for foundations, trenches, pools, and basements. It also drives equipment selection, trucking costs, and disposal fees.

Basic Formula

V = L Γ— W Γ— D (rectangular excavation). For trapezoidal trenches: V = [(W_top + W_bottom)/2] Γ— D Γ— L.

Swell Factor

Soil expands when excavated (swell). Clay: 30–40% swell. Sand: 10–15%. Rock: 50–70%. A 100 ydΒ³ clay excavation produces ~130 ydΒ³ of loose fill to haul.

Conversion

1 cubic yard = 27 cubic feet. Dump trucks typically carry 10–14 cubic yards per load.

Why Swell Factor Trips Up Budgets

Contractors who forget swell factor often under-budget hauling costs significantly β€” 100 cubic yards of in-place clay can swell to 130+ cubic yards once dug, meaning more truck trips (and disposal fees) than the original "hole size" volume suggests. This is one of the most common line-item cost overruns on excavation projects.

Compaction After Backfill

Confusingly, excavated soil that's later used as backfill compacts back down β€” often to 85–95% of its original in-place density, not 100%, since some structure of the original soil is permanently lost in the digging and re-placing process. This is why proper mechanical compaction (not just filling loosely) is required around foundations and utility trenches.